Sewer work that reaches the street needs a City of Littleton right-of-way permit, and the sanitation district that serves the property may have its own permit and inspection rules. Work in city right of way may also need a City of Littleton right of way permit.
Here is how the pieces fit.
1. The District Sewer Permit
The City of Littleton says it no longer issues permits specifically for sewer-related construction; a right-of-way permit is required instead when the work is in the street. The district then inspects the connection.
Why the district? The district owns the main your line connects to. It wants to see that the connection is tight and that nothing sticks into its pipe.
Do I need a permit to repair my sewer line in Littleton?
Yes. Check your sanitation district's own permit and inspection rules for service line repairs.
2. City Right of Way Permit
If the work reaches city right of way, such as the street or sidewalk, the city may require a right of way permit. The city notes this applies when work reaches City right of way in another district's service area. City Permit Center: (303) 795 3751.
Typical triggers:
- Digging in the street to reach the tap
- Cutting a sidewalk or curb
- Parking equipment in a travel lane
3. Emergency Work
When a line fails and must be fixed right away, work may start before every approval is in hand. The city asks for video or photo proof of the emergency with the permit application. Keep the camera footage.
4. Plumbing Permits
Plumbing work in Colorado needs a permit from the State Plumbing Board or the local building department. A plumbing contractor must pull permits under the company's name. A homeowner may pull a permit for work on their own residence.
5. Colorado 811 Locate
Before any digging, request a Colorado 811 locate at least three business days ahead. This is free and protects you and the crew from hitting gas or power lines.
District Notes Worth Knowing
- Grant Water and Sanitation District requires licensed plumbers and two working days notice before inspection.
- Valley Sanitation District requires licensing for lining that reaches the main.
- Columbine Water and Sanitation District checks contractor licensing at tap repairs.
- Highlands Ranch: the Metro District reviews projects that affect public water and sewer for Highlands Ranch Water, and Douglas County will not issue building permits without district approval.
Permit Checklist
- Find your sanitation district
- Confirm who pulls each permit
- Request Colorado 811 locates
- Schedule district inspection
- Keep before and after video
Common Questions
What happens if work is done without a permit? The district may require the line to be exposed for inspection. It can also cause trouble when you sell.
Do sewer scopes need a permit? A camera inspection alone usually does not. Repairs do.
Who calls 811, me or the contractor? The excavator is responsible. Confirm it is done.